Análisis experto de cuantificación de daños y retrasos en arbitraje internacional para FFIE

J.S. Held fortalece su experiencia en contabilidad forense para litigios matrimoniales y comerciales con la adquisición de Forensic Accountants & Consultants.

LEER MÁS cerrar Creado con Sketch.
Inicio·Análisis experto de cuantificación de daños y retrasos en arbitraje internacional para FFIE

La situación

As part of Colombia’s National Educational Infrastructure Plan, the Autonomous Educational Infrastructure Fund (FFIE) launched a program to design, develop, and construct approximately 248 educational facilities across Antioquia, the Coffee Region, the Pacific Region, and the Caribbean.

To deliver the program, FFIE executed three Framework Construction Contracts with the Mota-Engil Consortium (CME). These contracts covered the preparation of designs and technical studies, as well as the execution of the works through numerous individual Work Agreements. During the implementation, significant disputes emerged over contract administration, construction progress, invoicing, payments, contractual deductions, delays, and early termination of several Work Agreements.

As a result of these disputes, an international arbitration was initiated in October 2019, administered by the Bogotá Chamber of Commerce - Arbitration and Conciliation Center. In the arbitration, the Mota-Engil Consortium alleged contractual breaches and claimed technical, financial, and reputational damages.

Nuestro asesoramiento

J.S. Held delivered independent expert services supporting FFIE during the international arbitration. The scope included preparing expert rebuttal reports addressing opposing expert evidence; conducting delay and responsibility analyses; critically assessing and quantifying the damages claimed; supporting the counterclaim; and assisting during the document production phase. We also prepared and defended expert reports and provided technical support throughout the arbitral hearing and final submissions.

The engagement required evaluating a large-scale public infrastructure program composed of multiple simultaneous projects, characterized by significant technical and contractual complexity and high-value claims. This demanded close coordination between technical, financial, and legal teams.

Áreas de práctica relacionadas

> Resolución de conflictos y arbitraje internacional
Nuestros expertos apoyan a los clientes en la resolución de problemas desafiantes que pueden surgir en proyectos de ingeniería y construcción, a través de todas las formas de resolución de conflictos. Tenemos un compromiso inquebrantable de entregar las noticias en un análisis y testimonio claros y defendibles que aborden los problemas en cuestión.

 

> Consultoría de construcción
Brindamos experiencia en consultoría de construcción de proyectos de todo tipo y tamaño, así como de reclamaciones y disputas de diversas complejidades. Como expertos en resolución de conflictos de construcción, aprovechamos nuestro entendimiento de la industria de la construcción para evitar y, cuando sea necesario, identificar, evaluar y resolver las reclamaciones y disputas de construcción que puedan surgir.

CONTACTOS PRINCIPALES

For additional information about the engagement or to learn more about our services, contact:

Enrique Abiega
Ver biografía
Enrique Abiega
Director ejecutivo sénior| Líder de Asesoría en Construcción España y Latinoamérica
Jose Sobrini
Ver biografía
Jose Sobrini
Director | Asesoría en Construcción
Nuestros expertos